I-43 North-South Construction Update
About the Project:
The I-43 North-South Reconstruction project spans 14 miles from Silver Spring Drive north to WIS 60, in Milwaukee and Ozaukee counties. WisDOT is reconstructing I-43 to modern design standards and adding a lane in each direction. Additionally, five interchanges along the corridor will be reconstructed:
- Good Hope Road
- Brown Deer Road (constructing a new Diverging Diamond Interchange)
- County Line Road (constructing a new full-access interchange
- Mequon Road
- Pioneer Road (County C)
This project also includes:
- Construction of a brand-new interchange at Highland Road
- Replacement of the Union Pacific Railroad bridge over I-43 in Glendale
- Expansion of Port Washington Road in Glendale between Bender and Daphne roads
Progress Overview:
County Line Road Segment:
- Donges Bay Road, between County W (Port Washington Road) and just east of La Cresta Drive is scheduled to reopen in late September.
- Katherine Drive, north of Port Washington Road, is scheduled to close for approximately two months, shortly following the reopening of Donges Bay Road.
- Port Washington Road, between Port Washington Lane and County Line Road is scheduled to reopen early 2023.
- County Line Road entrance ramp to I-43 South is to remain closed through mid-2023.
- I-43 North exit ramp to Port Washington Road is to remain closed through mid-2023.
North End Segment:
- Highland Road, between County W (Port Washington Road) and Lake Shore Drive is scheduled to reopen early October.
- Highland Road Interchange ramps are scheduled to open to traffic late November.
What to expect to begin in early 2023:
County Line Road Segment:
- Close and rebuild County Line Road between Pheasant Lane and Port Washington Road through mid-2023.
- Southbound and northbound mainline freeway reconstruction just north and south of County Line Road.
- Close Port Washington Lane near County Line Road intersection through mid-2023.
- Reopen County Line Road entrance ramp to I-43 South in mid-2023.
- Reopen I-43 North exit ramp to Port Washington Road in mid-2023.
- Open Katherine Drive entrance ramp to I-43 North in mid-2023.
- Open I-43 South exit ramp to Port Washington Road in mid-2023.
Mequon Road Segment:
- Begin reconstruction of Mequon Road interchange
- Long-term lane closures on Mequon Road between Port Washington Road and Union Pacific Railroad.
- Shoulder closures on I-43 South for temporary widening.
North End Segment:
- Southbound and northbound mainline freeway reconstruction.
- Close and rebuild the County C (Pioneer Road) bridge and ramps.
- Short-term closures of Highland Road ramps (not concurrent with County C Ramps).
*All work is weather dependent and subject to change. Always check 511wi.gov prior to departure.
Stay Connected: Find us online at https://projects.511wi.gov/43north-south/